Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

Timing issue when using SOC Encounter

Status
Not open for further replies.

Haitham1988

Newbie level 4
Newbie level 4
Joined
May 8, 2010
Messages
5
Helped
0
Reputation
0
Reaction score
0
Trophy points
1,281
Location
cairo
Visit site
Activity points
1,313
Dear All,

When I check the timing by doing time analysis just before filling I get no violations, After applying the filling ( Metal filling ) I get four hold violations.
Does anyone have an explanation about the effect of metal filling on timing?!
I tried to do timing optimization to solve it but I does not work.

Thanks in advance,
Haitham
 

filling metal could impact the RC.
I guess for the metal filling you enable this option "addMetalFill -timingAware sta".
 

filling metal could impact the RC.
I guess for the metal filling you enable this option "addMetalFill -timingAware sta".

I think Metal filling is just floating metals and it should not affect RC
and I use the following command "addMetalFill -layer { 1 2 3 4} -squareShape"
So I think I am not using the mentioned option, Is it enabeled by default ?

Thanks for the response

Haitham
 

-timingAware could be on/off/sta, default is "on" which only take care of clock nets, less for signal nets, and don't care of power/ground nets.
"sta" mode take care of the critical net also, take more time, but better for a timing point of view.
 