Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

query in clock constraints

Status
Not open for further replies.

vsrpkumar

Member level 4
Joined
Mar 26, 2006
Messages
74
Helped
0
Reputation
0
Reaction score
0
Trophy points
1,286
Activity points
1,830
A system has 3 clocks inside and they are derived from main clock.In clock constraints, is it better to define them seperately or by derived clocks in primetime
kumar
 

i suggest to derive the clocks from the main clock, in this way you constraint is more consistant with the design and easy to follow.
 

Its better to define it as generated clocks. Because once you switch to post-layout this will ensure right network delay is calculated.
 