Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

Regarding Path groups in REPORT_QOR

Status
Not open for further replies.

tejanossam

Newbie level 1
Newbie level 1
Joined
Nov 17, 2009
Messages
1
Helped
0
Reputation
0
Reaction score
0
Trophy points
1,281
Location
INDIA
Visit site
Activity points
1,287
hi i have a problem regarding the path groups, after completing the cts stage when checking for summary of the voilations using the report_qor, it is giving the report only for the REGIN, REGOUT, and SCANCLK paths not for Main CLOCK, i didnt change any thing in the scripts it was giving in the previous runs but in the present run giving this problem, so can someone please help me by saying where may be the mistake and how to rectify it.
 

Status
Not open for further replies.

Part and Inventory Search

Welcome to EDABoard.com

Sponsor

Back
Top