Hi friend,
Half cycle path scenario like data Launch through +ve edge and Capture through _ve edge fp.
L-clk period 2: +ve edge is occurred 0 2 4 6 8 10
C-clk period 2: -Ve edge is occurred 1 3 5 7 9 11
Setup check: at edge 2 at L-clk : C-clk setup check edge 3
Hold check : at edge 2 at L-clk :C-clk hold check edge 1 ...it means in half cycle path hold check we will get half cycle more hold margin.So will get large +ve slack
Correct me if it is wrong