this is the question
the single line diagram of three phase power system is shown below ,the transformer capacity is 100MVAR and the rectance =20% on abase of 100MVAR ,23/115KV and the impedance Z=100j,the load at bus 2 is S2=184.8MW+6.6jMVAR ,and the bus 3 is S3=0MW+20jMVAR . it is required to hold the voltage at bus 3at 115KV.working in per unit ,determine the voltage at bus 2 and bus 1
THIS IS THE QUESTION AND THE DIAGRAM IN THE ATTACHMENT