Continue to Site

Welcome to EDAboard.com

Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

P-CAD, generating the report containing board statistics

Status
Not open for further replies.

Anonymous_Ricky

Advanced Member level 2
Joined
Dec 26, 2006
Messages
516
Helped
88
Reputation
178
Reaction score
58
Trophy points
1,308
Location
India
Activity points
3,974
P-CAD query

Hi all,

how can I generate the report containing board statistics (especially routing completion percentage) for board file.

regards,

Ricky
 

Re: P-CAD query

Anonymous_Ricky said:
Hi all,

how can I generate the report containing board statistics (especially routing completion percentage) for board file.

regards,

Ricky

How to determine if a board is fully routed.


Question:
How to tell if my board are routed 100%?


Possible answer:
Make all layers visible and all nets and components enabled for routing: Make all layers visible in Color Settings. If you added a Color Rule for any individual items on any layer, be sure they are visible. Enable all nets for routing in the Nets Spreadsheet. There should be a Yes in the Routing Enabled column for all nets. Enable for routing all Components in the Components Spreadsheet that have a net connection. Click on the Spreadsheet icon in the Toolbar and select Statistics. A chart will appear containing two columns. This may take some time if it is a large board. Check the numbers in the % Routed boxes. Both columns should match. If it says 100%, the board is fully routed. If not, look in the Unrouted and Partials boxes for the number of remaining nets that need to be routed. To find the nets that need to be routed, click on the Add/Edit Route Mode icon in the Toolbar, then hit the N key (for Next) on the keyboard. The cursor will jump to the first unrouted/partial net and you can finish routing it. Continue using the N key until you get a message All enabled nets are fully routed. Check Statistics again to be sure % Routed is 100%.
 
  • Like
Reactions: huivik

    huivik

    Points: 2
    Helpful Answer Positive Rating
Status
Not open for further replies.

Part and Inventory Search

Welcome to EDABoard.com

Sponsor

Back
Top