Welcome to our site! EDAboard.com is an international Electronics Discussion Forum focused on EDA software, circuits, schematics, books, theory, papers, asic, pld, 8051, DSP, Network, RF, Analog Design, PCB, Service Manuals... and a whole lot more! To participate you need to register. Registration is free. Click here to register now.

test point insertion

Status
Not open for further replies.

rajusripathi83

Junior Member level 2
Joined
Nov 26, 2012
Messages
22
Helped
0
Reputation
0
Reaction score
0
Trophy points
1,281
Activity points
1,441
please help me

for test point insertion below flow is correct or not ?

1--take rtl and do functionl verification......input=rtl,tb output=functional simulation out put file

2--take the rtl into dft compiler run with required constraints & generate un mapped netlist ........input=rtl,library ,,,output=unmapprd netlist

3--insert dft (define ports)

4--generate scan ready netlist......input=unmapped netlist, output=scan ready netlist

5--generate scan stitched netlist........input=scan ready netlist, output=scan stitched netlist

6--create test protocol file

7-- do physical design implementation up to routing.....input to ic compiler=scan stitched netlist, output=routed scan stitched netlist

8--the routed scan stitched netlist, simulation library & protocol file are taken into tetramax.....i/p=routed scan stitched netlist,library,protocol file

9--do simulation, & fault simulation (doubt ::::how to do simulation and fault simulation and how we will compare)

10--find the undetected faults

11--find location of undetectable faults

12--analyze the results

13--for inserting user defined test points go to dft compiler (doubt::::::where we need to go step 2 or 3 or 4 or 5 or 6 or 7)

14--insert the test points

15--repeat the step 5 to step 12


is the flow is correct

and what are the inputs and outputs at each stage.
 

Fault Simulation is performed after the pattern generation.We simulate the pattern,for confirming that there is not any mismatches in the Patterns. means we are checking that the generated Patterns are passing or not.Fault Simulation is done in the TetraMAX itself.

And the Simulation is performed for the functional testing.The circuit is functioning properly or not.

- - - Updated - - -

please help me

for test point insertion below flow is correct or not ?

8--the routed scan stitched netlist, simulation library & protocol file are taken into tetramax.....i/p=routed scan stitched netlist,library,protocol file

9--do simulation, & fault simulation (doubt ::::how to do simulation and fault simulation and how we will compare)

10--find the undetected faults

11--find location of undetectable faults

12--analyze the results

13--for inserting user defined test points go to dft compiler (doubt::::::where we need to go step 2 or 3 or 4 or 5 or 6 or 7)

14--insert the test points

15--repeat the step 5 to step 12


is the flow is correct

and what are the inputs and outputs at each stage.

9) Fault Simulation is done in TetraMAX ATPG itself.And the simulation is done with the VCS or any other simulator.

13) Whenever we got that at this instance we need to add test point,we have to do it using Design Compiler on the final routed netlist.
 
Status